[Federal Register: March 7, 2003 (Volume 68, Number 45)]
[Notices]
[Page 11072-11073]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr07mr03-61]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP02-396-000 and PF01-1-000]
Greenbrier Pipeline Company, LLC; Notice of Availability of the
Final Environmental Impact Statement for the Proposed Greenbrier
Pipeline Project
February 28, 2003.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) has prepared this final environmental impact statement
(FEIS) on the natural gas pipeline facilities (the Greenbrier Pipeline
Project) proposed by Greenbrier Pipeline Company, LLC (GPC) in the
above-referenced dockets. The application and other supplemental
filings in these dockets are available for viewing on the FERC Internet
Web site (http://frwebgate.access.gpo.gov/cgi-bin/leaving.cgi?from=leavingFR.html&log=linklog&to=http://www.ferc.gov). Click on the ``FERRIS'' link, select
Web site (http://http://frwebgate.access.gpo.gov/cgi-bin/leaving.cgi?from=leavingFR.html&log=linklog&to=www.ferc.gov). Click on the ``FERRIS'' link, select
``General Search,'' then ``Docket '' on the menu, and follow
the instructions.
The FEIS was prepared to satisfy the requirements of the National
Environmental Policy Act (NEPA). The staff concludes that approval of
the proposed project with appropriate mitigating measures, as
recommended, would result in some adverse environmental impacts. The
FEIS evaluates alternatives to the proposal, including system
alternatives, route alternatives, and route variations.
The purpose of the project is to create gas supply diversity and to
meet a portion of the growing energy market in the South Atlantic
region. The project would be designed to meet a variety of anticipated
loads, including the growth of two local distribution companies, four
natural gas-fired electric generation plants, and a natural gas
marketer. The project is fully subscribed and would transport up to
600,000 decatherms per day of natural gas.
The proposed pipeline would extend from east of Clendenin, Kanawha
County, West Virginia, through West Virginia, southwestern Virginia,
and North Carolina to its terminus near Stem, in Granville County,
North Carolina. It would consist of 275.6 miles
[[Page 11073]]
of mainline and three laterals totaling 3.8 miles. The project would
also construct 2 compressor stations, 3 meter stations, 18 stand alone
block valves (additional block valves would be collocated at other
aboveground facility sites), and appurtenant facilities, and about 212
access roads. Mainline DG-1 would extend from the proposed Elk River
Compressor Station adjacent to Dominion Transmission, Inc.''s existing
Cornwell Compressor Station to the proposed Public Service Company of
North Carolina, Inc., a South Carolina Corporation's compressor station
near Stem, North Carolina. DG-1 would include 20-, 24-, and 30-inch-
diameter pipeline. Lateral DG-2 would consist of 12-inch-diameter
pipeline that extends from DG-1 to the proposed Somerset Meter Station
near Roxboro, North Carolina. Lateral DG-3 would consist of 10-inch-
diameter pipeline that extends from the end of DG-1 to the proposed
Mountain Creek Meter Station near Butner, North Carolina. Lateral DG-4
would consist of 30-inch-diameter pipeline that would interconnect the
proposed Transco Meter Station and the proposed Eden Compressor Station
in Rockingham County, North Carolina.
The FEIS has been placed in the public files of the FERC and is
available for distribution and public inspection at: Federal Energy
Regulatory Commission, Public Reference and Files Maintenance Branch,
888 First Street, NE., Room 2A, Washington, DC 20426, (202) 502-8371.
E-mail: public.referenceroom@ferc.gov.
A limited number of copies are available from the Public Reference
and Files Maintenance Branch identified above. In addition, copies of
the FEIS have been mailed to Federal, State, and local government
agencies; elected officials, environmental and public interest groups;
affected landowners who requested a copy of the FEIS; Native American
tribes that might attach religious and cultural significance to
historic properties in the area of potential effect; local libraries
and newspapers; and the Commission's list of parties to this
proceeding.
In accordance with the Council on Environmental Quality (CEQ)
regulations implementing the National Environmental Policy Act, no
agency decision on a proposed action may be made until 30 days after
the U.S. Environmental Protection Agency publishes a notice of
availability of the FEIS. However, the CEQ regulations provide an
exception to this rule when an agency decision is subject to a formal
internal process which allows other agencies or the public to make
their views known. In such cases, the agency decision may be made at
the same time the notice of the FEIS is published, allowing both
periods to run concurrently. The Commission decision for this proposed
action is subject to a 30-day rehearing period.
Additional information about the proposed project is available from
the Commission's Office of External Affairs, at 1-866-208-3372 or on
the FERC Internet Web site (http://frwebgate.access.gpo.gov/cgi-bin/leaving.cgi?from=leavingFR.html&log=linklog&to=www.ferc.gov), using the ``FERRIS'' link to
information in this docket number. Click on the ``FERRIS'' link, select
``General Search'' from the menu, and follow the instructions. For
assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676 or for TYY
contact 1-202-502-8659. The FERRIS link on the FERC Internet Web site
also provides access to the texts of formal documents issued by the
Commission, such as orders, notices, and rulemakings.
Magalie R. Salas,
Secretary.
[FR Doc. 03-5373 Filed 3-6-03; 8:45 am]
BILLING CODE 6717-01-P